Project: 3 Starbuck Cafes. Wales

Client: KPS

Details: site prep, foundations, internal and external slabs, drainage, services, 278 works, block paving, kerbing, street furniture and landscaping. 

Approx Value: £750k

Approx Duration: 32 weeks 

Project: 2 Industrial Units, Newport

Client: Benniman

Details: Drainage, retaining walls, foundations, pile caps, concrete service yards, internal office slabs, upper floor concrete, concrete paths, services, kerbing and paving 

Approx Value: £1.0mil

Approx Duration: 28 weeks 

Project: 2 Industrial Units Haverhill Business Park

Client: A&H Construction

Details: Deep drainage, attenuation tanks, foundations, concrete service yards, internal office slabs, services, kerbing and paving, 278 works  

Approx Value: £1mil

Approx Duration: 28 weeks 

Project: The Gym. Stourbridge

Client: APP Construction

Details: Cut, fill and site clearance. retaning walls (in situ) headwalls, attenuation tanks, deep drainage, services, foundations, internla and external slabs, flag paving and street furniture 

Approx Value: £550k

Approx Duration: 16 weeks 

Project: Blythe Valley - Office Block & Car Park

Client: Benniman Construction

Details: Site Strip, Cut and fill, soil stabilisation and ground modification, Deep Drainage, Foundations, Internal concrete Slabs, Permeable Paving and associated drainage, services, street furniture, decorative block paving, road works and services. 

Approx Value: £500k 

Approx Duration: 25 weeks

Project: Costa Coffee Drive Thru, Coventry. 

Client: KPS

Details: Site preparation, drainage, foundations, internal concrete slab and external concrete slabs. services, block paving and street furniture. jlg have commenced section 38 access road works also.

Approx Value: £200k 

Approx Duration: 13 weeks

Project: Roads and sewers powick new housing estate 

Client: Seddon Construction

Details: Deep drainage, services, access road works to highways standards; kerbing; edgings; drainage kerbs, attenuation and filling capping layers to underside of tarmac

Approx Value: £1mil

Approx Duration: 28 weeks

Project: Sea Scouts Warwick

Client: Greswolde Construction

Details: Cut & fill, site preparation; drainage , services, external works including paving, kerbing. jlg also undertook the internal slab to fm2 special tolerance. 

Approx Value: £400k

Approx Duration: 16 weeks